The California Independent System Operator (CAISO) is the largest ISO of about 38 balancing authorities in the western interconnection, handling over two-thirds of the electric load in the West.

In collaboration with the California Public Utilities Commission (CPUC) and the California Energy Commission (CEC), CAISO recently published its first-ever draft 20-Year Transmission Outlook, with a focus on providing a longer-term view of transmission needed to reliably meet state clean energy goals. California’s 100 Percent Clean Energy Act of 2018 or Senate Bill 100 (SB 100) calls for a switch over to carbon-free electricity by 2045, in addition to accelerating the integration of new renewable electricity resources into the grid. It also aims to ensure at least 60 per cent of California’s electricity is renewable by 2030.

The draft develops a long-range blueprint of the interconnected high-voltage wires required to meet the above goals. It was conducted in parallel with the CAISO’s customary annual 10-year transmission planning process (TPP). The draft outlook was open to stakeholder feedback until February 22, 2022 and will be finalised in March 2022 in parallel with CAISO’s 2022-23 Transmission Plan.

It envisages an investment of USD30.5 billion in transmission, with over 65 per cent (USD19.76 billion) being allocated to integration of offshore wind as well as out-of-state wind. The remaining will be invested in upgrading the existing transmission infrastructure in CAISO’s footprint.

CAISO’s current footprint

CAISO manages the flow of electricity across the high-voltage, long-distance power lines for the grid serving 80 per cent of California and a small part of Nevada. As the only independent grid operator in the western US, it provides equal access to roughly 26,000 circuit miles (41,843 km) of transmission lines and coordinates competing and diverse energy resources into the grid. The transmission network under its jurisdiction operates across several voltages, including 70 kV, 115 kV, 230 kV and 500 kV. Three investor-owned utilities (IOUs) fall under CAISO’s jurisdiction – Pacific Gas & Electric (PG&E), Southern California Edison (SCE) and San Diego Gas and Electric (SDG&E).

Key drivers for long-term planning

CAISO has witnessed an increase in the demand for new transmission particularly over the last couple of years. For instance, while the 2020-21 transmission plan was based on a 10-year projection of adding 1 GW annually, the 2021-22 plan is based on a projection of adding 2.7 GW per year, and current drafts being proposed for the 2022-23 plan call for additions of over 4 GW per year. The accelerating resource requirements over the next 10 years are driven by several circumstances, including the need to decarbonise the electricity grid; the expected electrification of transportation and other carbon-emitting industries driving up electricity demand forecasts; issues related to reduced access to imports as neighbouring systems also decarbonise; higher than anticipated impact of shift in the peak loads due to increased solar penetration; as well as the need to maintain system reliability in light of retiring gas-fired generation and the Diablo Canyon nuclear power plant.

In addition to solar power and battery storage, other resources including geothermal, offshore wind and out-of-state wind resources are expected to play a greater role and create unique challenges in planning and interconnection processes. Addressing these challenges will require adaptations and enhancements to existing processes and efforts. Currently, a whopping 605 projects aggregating 2,36,225 MW are in CAISO’s interconnection queue. This level of hyper competition hinders integration of the resources that must be added to the grid and thus imposes greater pressure on resources of the ISO and transmission owners.

In this context, the draft 20-Year Transmission Outlook essentially provides a long-term conceptual plan for the transmission grid, matched with state agency input on integrated load forecasting and resource planning, to meet resource and electric load needs.

Key assumptions and transmission needs

The draft 20-Year Transmission Outlook provides a baseline architecture for future planning activities. It includes high-level technical studies to test feasibility of alternatives, focusing on the bulk transmission system.

The report uses a Starting Point scenario, which is based on 2021 SB 100 Joint Agency Report (2021 SB 100 Report) published jointly by CEC, CPUC and California Air Resources Board (CARB) in line with the SB 100 mandate. CAISO coordinated with the joint agencies on the next steps to plan for the SB 100-driven resource build that has been used as input for the outlook. This included workshops on potential transmission projects and resource mapping.

This Starting Point scenario includes diverse resources known to require transmission development such as offshore wind energy, out-of-state resources and geothermal. It also takes into account gas power plant retirements that may require transmission development to reduce local area constraints. The scenario is based on 2040 SB 100 Core scenario and was created by increasing the expected natural gas power plant retirements to 15,000 MW. Additionally, to generally offset the additional assumed natural gas power plant retirements, geothermal, offshore wind, out-of-state wind and battery energy storage systems capacity was added to levels that are generally reflective of other 2021 SB 100 Report scenarios.

On the demand side, CAISO started with the SB 100 Core state-wide high electrification load projection, in which the 2040 peak load is 82,364 MW. This represents a 28.5 per cent increase from CEC’s Integrated Energy Policy Report (IEPR) 2020 load forecast of 64,076 MW in 2031. The load to be served by the system was then again lowered by the forecast of behind-the-meter resources.

The resulting transmission plan calls for significant 500 kV AC and high voltage direct current (HVDC) development to access offshore wind and out-of-state wind, and reinforce the existing CAISO footprint.  

Offshore wind 

According to the outlook, 10 GW of offshore wind will be developed in California including 6,000 MW in Diablo Canyon and Morro Bay call areas on the central coast and 4,000 MW in Humboldt call areas on the north coast. The offshore wind resources on the north coast will require significant 500 kV HVDC facilities to interconnect to CAISO’s existing 500 kV system. CAISO has identified the need for two 500 kV AC lines connecting to the 500 kV Fern Road substation and a HVDC line to the 500/230 kV Collinsville substation. Another alternative considered in the CAISO’s 2021-2022 Transmission Plan is an HVDC-voltage source converter (VSC) deep sea cable to a new Bay Hub station located in the Greater Bay Area. The central coast offshore wind capacity will be interconnected to the existing 500 kV Diablo substation and a new 500 kV Morro Bay substation looping in the existing 500 kV Diablo–Gates line.

Out-of-state wind

To interconnect out-of-state wind to the CAISO grid, it has identified new transmission to link 9,900 MW from Wyoming (4,685 MW) and New Mexico (5,215 MW). Further, another 2,100 MW from the northwest (1,500 MW) and Baja California (600 MW) will be connected to existing transmission. Some of the identified transmission projects include Southwest Intertie Project-North (SWIP-North), Cross-Tie, Robinson-Eldorado, TransWest Express, and additional transmission for additional wind resources from Wyoming/Idaho and New Mexico area.

Upgrades to existing lines

CAISO has planned upgrades of 14 existing transmission projects in its footprint at an investment of USD10.74 billion. Majority of these lines are at 500 kV and represent a total line length of 1,558 km. Key upgrade projects are the Eldorado–Lugo line, the Colorado River–Devers line, the Second Los Banos–Tracy line, the Manning–Moss Landing line, the Diablo–North HVDC project, the Diablo–South HVDC project and the 500/230 kV Round Mountain and Lugo transformers. Key developers include SCE, DCR Transmission LLC and Duke-American Transmission Company.

Investment requirements

The cost estimate of transmission development to integrate the resources in the SB 100 Starting Point scenario has been identified at USD30.5 billion.

The way forward

In a bid to explore the longer-term grid requirements and options to achieve the state’s 2045 objectives, CAISO’s draft 20-Year Transmission Outlook has identified the system needs by mapping resources aggregating 120.8 GW to the appropriate regions as well as the transmission additions necessary to add those resources to the grid, and then examined the need to deliver those resources over the bulk transmission system.

CAISO’s outlook is intended to help scope the challenges faced by the ISO, help the state to further refine resource planning, and provide longer term context for decisions made in the 10-year TPP. Essentially, it provides a long-term conceptual plan of the transmission grid in 20 years and forms the basis for further dialogue. After finalising this draft in March 2022, CAISO intends to continue the discussion on the findings in ongoing SB 100 processes; collect input on issues and parameters that could be considered and refined in a future outlook development cycle; and provide an update on the 20-year outlook activities and communicate intentions going forward by the end of 2022.

The state has exciting times ahead as it aligns its transmission planning and development to meet the requirements posed by California’s ambitious climate and energy goals.