OCI Energy has sold Project Clairemont, a 327 MWdc solar project which is currently under development in Kent County, Texas, to Hyundai Engineering Company Limited. Construction of Project Clairemont is expected to begin in the third quarter of 2027, with completion scheduled for the third quarter of 2029. This marks the second transaction between the two companies, following the sale of Project Hillsboro, a 260 MWdc solar project in Hill County, Texas, by OCI Energy to Hyundai Engineering in 2024.

Earlier, in September 2026, OCI Energy, Arava Power, and partners broke ground on the SunRoper solar project in Wharton County, Texas. The project has an installed capacity of 347 MWdc and is expected to commence operations in December 2027.

In May 2026, OCI Energy and Arava Power signed a purchase agreement for the 670 MWdc La Salle Solar project. The project is located in La Salle County, Texas. Under the agreement, Arava Power will acquire a 50 per cent stake in the project, with both companies jointly financing, constructing, owning, and operating the plant.